1. DEADLINES AND TIMELINES
Is it possible to revise or extend the deadlines for submitting the 2027–2030 Strategy (June 30, 2026) and 2030–2036 Strategy (September 15, 2026)? Are these the only milestones envisaged, or are additional interim deliverables expected? What is the expected contract award date and project start date?
It is currently not possible to revise or extend the Strategy submission deadlines. If the deadlines are extended, we will inform the bidders. Interim stages are expected, during which the consultant plans to discuss the completed studies and work in detail through a presentation. Specific contract award and project start dates will be determined after the evaluation is completed. The client will communicate a confirmed schedule after internal approval.
2. PROJECT BUDGET
The Terms of Reference do not specify an estimated project budget. Can the Client provide a budget or expected effort benchmark to ensure comparability of proposals?
The budget is based on the best price offers based on the scope of work specified in the Terms of reference.
3. LEVEL OF DETAIL OF THE STRATEGY
1. Should the Strategy remain at a conceptual level for the entire airport system, or are recommendations for each individual airport expected? What is the expected level of detail—a strategic framework or a quantitative analysis?
The Client expects recommendations to be prepared at the national level, in a consolidated form, with an action plan for each airport.
2. For the areas of CX, KPIs, ESG, corporate governance, and financial sustainability, is it necessary to develop only principles or also detailed implementation plans for each airport?
In accordance with paragraphs 1 and 2.1 of the Terms of Reference, the strategy being developed must be a single document at the national system level, rather than a collection of individual strategies for each airport.
The expected level of detail requires the development of practical mechanisms and roadmaps for each airport.
3. Who is the primary user of the project's deliverables? Is it necessary to prepare separate deliverables for the Cabinet of Ministers or the Ministry of Transport?
The client of the strategy is Uzbekistan Airports JSC. Separate deliverables for government agencies are not required. JSC will independently adapt the documents for the government.
4. DATA AVAILABILITY
Will historical operating, financial, and traffic data be provided for all 19 airports (including PPPs/concessions)? Is data on non-aviation revenues, operating expenses, financial statements, aviation charges, and KPIs available for each airport separately? Will access be provided to current PPP/concession agreements, master plans, technical drawings, certification documentation, existing studies, and master plans for all airports?
The client will provide accessible data upon the consultant's request after approval by management and the signing of an NDA. Open data is also published on the JSC's official website.
5. TRAFFIC FORECASTING AND FINANCIAL MODELING
Should traffic forecasting be developed only at the national level, for each airport, or for each airport with multiple scenarios? Which methodology is preferred? Is a full-fledged financial model for the entire system expected, or only a strategic framework? Are quantitative tariff scenarios required?
For each airport with multiple scenarios. The client expects the development of a robust financial model (at the asset portfolio/corporate center level). While the model should not descend to the micro-level of each small regional facility, it should serve as a working quantitative tool for making management decisions on tariffs, CAPEX prioritization, and raising debt/private capital across the entire network over a 10-year horizon.
6. PPP AND PRIVATE SECTOR INVOLVEMENT
Is a detailed analysis of existing PPP contracts required, or are policy-level recommendations sufficient? Are recommendations needed for the transfer of specific airports to concession, or only general principles?
The Client does not require an in-depth review of existing contracts for revision. The Consultant's task is to develop a unified guide/methodology for the asset owner: how to monitor current concessionaires, how to structure risks in future PPP transactions, and how to safely return assets to state control upon contract expiration. The Client expects the development of a systemic methodology: how to structure risks for JSCs, how to monitor the fulfillment of investment obligations by concessionaires, and how to protect public interests. Recommendations on the transfer of specific airports to concession are also welcome.
Navoi Airport is not excluded from the scope of the tender. https://lex.uz/ru/docs/8040601
7. ESG AND SUSTAINABLE DEVELOPMENT
Is an overall ESG strategy required, or individual ones for each airport? Is a strategic framework sufficient, or are practical mechanisms required? Are Net Zero 2050 and ESG KPIs independent?
In accordance with paragraphs 1 and 2.1 of the Terms of Reference, the strategy being developed must be a single document at the national system level, not a collection of individual strategies for each airport. We expect a fully integrated approach. Climate goals (Net Zero) must be digitized, translated into specific ESG KPIs, and integrated into the overall corporate governance system of the national airport network.
8. AVIATION SECURITY (AVSEC) AND FLIGHT SAFETY MANAGEMENT SYSTEM (SMS)
What level of detail is expected for the SMS: only a strategic framework or an airport-by-airport assessment of compliance?
The client expects the development of a strategic framework and SMS Roadmap at the corporate level in accordance with ICAO standards. The air navigation component is overseen by a separate structure; we expect recommendations regarding the JSC's activities. Your responsibilities in this section do not include the engineering and technical development of ATC/ANS systems or the design of hardware and software safety systems. You are solely developing a corporate Roadmap and strategic framework for the implementation of the Safety Management System (SMS).
9. ORGANIZING MEETINGS AND SITE VISITS
How many working meetings and presentations are planned? Is it necessary to visit all 19 airports, or is a representative sample sufficient? Will the Client coordinate access to ministries and PPP operators?
There is no set number of working meetings; they will be organized at the consultant's request. Working meetings are planned in any convenient format, but a travel budget must be specified separately in the proposal.
10. SIMULATION MODELLING
Simulation modeling is completely excluded from the strategy development requirements.
11. HUMAN RESOURCES / INSTITUTIONAL DEVELOPMENT
Human resources planning—system-wide or airport-by-airport? Are training programs expected to be developed or implemented?
The Client does not expect a human resources audit of each workstation or a detailed headcount calculation at each airport. The Consultant's task is to develop a unified corporate methodology for human capital management: to identify the strategic need for new competencies over the next 10 years, propose targeted training programs, and build mechanisms for institutional strengthening of both the company itself and airport operators.
27 Mar, 2026
10 Apr, 2026